In StormCAD I entered a global storm event for the system; however, it doesn't run the model for the entire storm event. I give the time of concentration and it models the storm at that exact moment. I want it to run the storm for the entire global storm event, which is one hour.
Hello Patrick,
StormCAD performs a steady state (peak flow) analysis. If you are looking for an extended period simulation then I suggest looking into SewerGEMS or CivilStorm.
See: Differences between solvers: GVF-Convex vs. GVF-Rational vs. Implicit vs. Explicit (SWMM)
"The StormCAD product (and the GVF Rational Solver in SewerGEMS and CivilStorm) uses the rational method to analyze or design a system under peak flow conditions based on peak rainfall intensity, while the other solvers in CivilStorm and SewerGEMS such as the Implicit or Explicit, takes rainfall hyetographs (rain vs. time) and develops hydrographs (flow vs. time) for each pipe and routes the flows dynamically. If you are studying a small area where only peak flow is of interest, or if you need to design a system based on the standard rational method, then StormCAD or the StormCAD solver (GVF Rational) should be adequate. If you are working on a large area where hydrograph routing and storage are significant, where you need to use a dynamic solver, or if you need to otherwise analyze more complex effects such as flooding and controls structures, then the Implicit and Explicit solvers in CivilStorm (or SewerGEMS) is what you need."
Regards,
Craig Calvin
Bentley Technical Support