Hi Guys,
I have a doubt in my water gem model. Currently, we are working in the industrial area project, So Each building has specific demand. I provided specific demand to the relative required nodes. My doubt their lot fo nodes has no demand required so I didn't provide any demand. Please confirm whether this is correct or not?. I have attached my mode5.9_Industrial_IrrigationStudy_AppA_WaterGEM.zipl for review.
Hello Ragavendra,
There does not seem to be any issue with the model, by looking at the results. Model results look correct.
You have demand entered only for the end-node junctions, which is fine as it is not necessary to have demand at every junctions if it is not the case on field as well.
Here is information about FAQ of WaterGEMS, for your reference.
Learning Resource Guide for new users of Bentley WaterGEMS and WaterCAD
Regards,
Sushma Choure
Bentley Technical Suppport
Answer Verified By: Ragavendra V
Hi Sushma..
Thank you so much.... Just want to know am going in right direction...