Hello,
We have used WaterGEMS v8i to model an existing network which has to be upgraded/improved.
We wish to model one option which is splitting the exiting network into 2 independent ones - an upper and a lower network which will be isolated by a new valve.
Can both networks be run on a single model/wgems file in parallel instead of creating a model for each network?
The easiest way to do this may be to use Active Topology and set one system to Inactive in one scenario and the other to Inactive in another scenario while you keep a base scenario with everything.
You could also make several copies of the model files and delete everything that is not needed for each partial model.
Answer Verified By: Sushma Choure
OK, we will try the using Active Topology. Thank you!