Compute reports are not one hour intervals

I use watergems, why when I compute the results it doesn't come out at one hour intervals as shown below. 
Compute Report
I have set the pattern for one hour intervals for 24 hours running.
Pattern
how can i fix this thank you
Parents
  • Intermediate time steps are reported when there are important changes in model calculations, or say pumps turn off / on, tanks becomes empty / full at that time step. Which helps you in taking your modeling decisions.

    As mentioned by Gary you can change the reported time step constant - 1 hr through calculation options. Currently reporting step must be set to all, which means report all time step which are important and where hydraulic changes take place. 

    Also here are some WaterGEMS learning resources for your reference. 

    Learning Resource Guide for new users of Bentley WaterGEMS and WaterCAD 

    Regards,

    Sushma Choure

    Bentley Technical Suppport

Reply
  • Intermediate time steps are reported when there are important changes in model calculations, or say pumps turn off / on, tanks becomes empty / full at that time step. Which helps you in taking your modeling decisions.

    As mentioned by Gary you can change the reported time step constant - 1 hr through calculation options. Currently reporting step must be set to all, which means report all time step which are important and where hydraulic changes take place. 

    Also here are some WaterGEMS learning resources for your reference. 

    Learning Resource Guide for new users of Bentley WaterGEMS and WaterCAD 

    Regards,

    Sushma Choure