When using the Skelebrator feature Series Pipe Merging, two pipes that appear to satisfy the parameters entered are not merging as expected.Problem ID#: 62529
Verify that the pipes that should be merging are not perpendicular toanother pipe. In cases where two pipes that fit the parameters are at atee with another pipe, the merge will not go through. This is because inthe series pipe merge process, the conjoining junction is removed andthe two pipes are replaced with a single pipe. However, as the junctionat the tee is also the end node of the perpendicular pipe, it cannot beremoved.
Series Pipe Merging in Skelebrator not working for pipes with zero diameter