How can I set up pre-development and post-development scenarios for use in pond design with PondMaker?
I want to design the pond using the tool PondMaker, for that I need to setup the model for pre-development conditions and post-development conditions. I need to use the scenarios to set this up.
Create New Pre/Post-Development Scenarios Dialog
This dialog allows you to quickly create scenarios alternatives for pre- and post-development conditions.
This dialogue pops up in CivilStorm if you are creating a new model, for SewerGEMS you can access it through Analysis > scenarios > New button > New Pre/post scenarios.
The dialog consists of the following controls:
Click the Create button to generate the specified scenarios and alternatives; click Cancel to close the dialog without creating scenarios or alternatives.
Example
Based on the following parameters:
The following scenarios will be created:
And the following alternatives will be created:
Creating Your Pre-Development Network
You need to create a Pre-Development network so you can calculate your target peak runoff flows for use in the Post-Development environment.
4.Click the File menu and select Save.
Creating Your Post-Development Network
You need to create a Post-Development network that represents the situation for which you have to design your detention and/or retention ponds and outlet structures.
To model the elements that will be used in the Post-Development scenarios but aren't used in the Pre-Development ones we will use the active topology feature. Active topology allows you to make an element or elements inactive in one or more scenarios. When an element is inactive, it has no effect on the model calculations.
3.Click the Layout button and select Pond Outlet from the submenu.
4.Click to place the pond outlet somewhere inside the borders of the pond. Click on the outfall O-1 to connect the pond outlet to the outfall, then right-click and select Done.
5.Highlight the catchment CM-1 and change the Outflow Node property to pond PO-1.
6.Now the Post-Development network is laid out. Change the Active Scenario to Post-Development 25. Note that the changes you made to the Post-Development 2 scenario have been inherited by the Post-Development 25 scenario.
7.Change the Active Scenario to Pre-Development 2. Note that the pond and the pond outlet are greyed out; this indicates that these elements are inactive in the current scenario, and will have no effect on the calculations.
8.Save the project.
9. Next, select the Post-development scenario as the active scenario and use PondMaker to design the pond.
Scenario and alternative management
Using PondMaker