How to Reorder Iso Sheet Numbering Using Pipeline Start Note in OpenPlant Modeler


Applies To 
Product(s): OpenPlant Modeler
Version(s): 08.11.11.87 (SS6) & Above
Environment: Windows 7/8.1/10 (64 bit)
Area: component
Subarea: Place Note - Pipeline Start Point
Original Author: Rahul Kumar, Bentley Product Advantage Group

Background

Introducing new tool in OpenPlant Modeler under “Place Note” option, which can control the order of Iso sheets generated in Pipeline Manager using, “AutoGenerate Iso-Sheet” option. To verify the result, generate Iso-Sheet with default setting through pipeline Manager using “AutoGenerate Iso-Sheet” option. Notice the Iso-Sheet assigned by default. See image below. 

See below steps described in detail to re-order the Iso-sheet as per choice. 

Steps to Accomplish

  1. Launch OpenPlant Modeler & select required Project Unit.

  2. Under Piping Tab, Select Pipe Note.

  3. Use option, “Pipeline Start Point”.

  4. Place it at the Start Point of Pipeline to enable it to start creating Iso Sheet from that point. See image below. 


  5. In Pipeline Manager, select pipeline and use option “AutoGenerate Iso-Sheet”.

  6. Verify Iso-Sheet created in Iso-Sheet Manager dialog box. See image below. 



  7. Publish an i-model and generate Isometric output. 

See Also

communities.bentley.com/.../component---openplant-modeler

Comments or Corrections?