Overview
PIECE_MARK is not an updatable field from “Update from Spec”. The field can be updated from “Update Component” Piping>Database Tools>Update Component once the following have been implemented.
Before PIECE_MARK can be updated though the Update Component dialog PIECE_MARK must be changed to an updateable field. Use the following steps to change PIECE_MARK to an updatable field:
1.Open Project Administrator
2.Select the Project
3.Expand the Project
4.Go to Database>Database
5.Select PROJDATA then Edit Tables
6.In the dialog choose PIPING then choose Columns
7.Select PIECE_MARK and change the column “Allow User Updates” to Yes
8.Save and close the project
In piping add PIECE_MARK as a field that can be updated
1.Go to Piping>Setup>Component Update Preferences
2.Add PIECE_MARK to Fields To Include
3.Ok and exit
PIECE_MARK can now be updated from Update Component.
Bentley Technical Support KnowledgeBase
Bentley LEARN Server
Bentley's Technical Support Group requests that you please confine any comments you have on this Wiki entry to this "Comments or Corrections?" section. THANK YOU!