While working on design projects, there might be cases where equipment and raceway models require changes. The changes might be in the position of equipment, changes in properties of equipment and raceways or adding additional raceway segments or equipment. These changes need to be reflected for routing of the cables.In such cases, there is no need to build the complete routing model after making changes to equipment and raceway models.Cable Manager in Bentley Raceway and Cable Management provides a tool to reflect the changes done to equipment and raceway without the need of re-building the complete routing model.
1.Launch Bentley Raceway and Cable Management and make the required changes to the equipment and raceway files.
2.Open Routing.dgn file.3.Click on Cable Manager and using the collaboration manager, request lock the equipment and raceway files required for routing of the cables.
4.To make the changes made to the equipment and raceway files reflect in the routing model, Click on Refresh Model. 5. The routing model will be updated with the changes made in the equipment and raceway model and cable routing can be done.
If above problem still persists, then please create a Service Request and contact the Bentley Product Advantage group. Please include a list of all relevant details to get in depth analysis for a solution or workaround.