How to set Storage Path of Isometrics in Managed Workspace OPIM CE


Applies To 
Product(s):OpenPlant Isometrics Manager CE
Version(s):10.9.1.6 or the latest
Environment: Windows 10 (64 bit)
Area: Isometric Drawing Generation
Subarea: ProjectWise Integration
Original Author:Fer Mykiel Gonzales, Bentley Technical Support Group

Background

Once the isometric drawing is generated, the user wants to post the dgn to their ProjectWise datasource preferred storage location. 

Steps To Accomplish

1. Open a dgn that belongs to the Managed Workspace

2. Generate an isometric of any pipeline

3. Once the isometric drawing is generated, open Launch Project Configuration

4. Under ProjectWise Settings, set the location of the storage folder in the Managed Workspace.

5. Save the Project Configuration

6. Close the OPIM dialog

7. Generate isometric drawing again 

8. Post the dgn to ProjectWise. Either by Posting all isometrics or by individually right clicking the dgn and post to ProjectWise.

OR

9. In ProjectWise Explorer, browse to the selected folder set in step 4. The isometric dgn will be located to 3 subfolders, namely the Service, then Unit, and finally in Pipeline Name.

Still a Problem?

If the above problem still persists, then please create a Case and contact the Bentley Technical Support Group.  Please include a list of all relevant details to get in depth analysis for a solution or workaround.