Hi All,
I am currently working inside ProjectWise . Meanwhile, I have been working on the current version of a document for about five days now but I want to restore the document back to how it was three days ago.
How do I achieve this on ProjectWise?
Any suggestions would help.
Thank you
Regards
Henry
Also, if you have not been checking in the file or doing an "Update Server Copy" of the file, the server will not have any of the changes you've made in the last 5 days.