Power Outage

We are having a planned power outage.  IT is planning to shutdown the ProjectWise servers before hand.  Question: should the ProjectWise server software be shutdown first?

Parents
  • Hi Neil,

    We are running several supporting servers server including DCS.

    We prefere to shut down all the supporting servers any order first, then the main integration server then shut down the database server.  

    Then power up in reserve order so database server first then main integration server when windows/pw is really started, power up the supporting servers any order.

    For our remote offices we sometimes see a need to restart the caching server\service if the main intergration server is shut down.

    Answer Verified By: Neil Norberg 

Reply
  • Hi Neil,

    We are running several supporting servers server including DCS.

    We prefere to shut down all the supporting servers any order first, then the main integration server then shut down the database server.  

    Then power up in reserve order so database server first then main integration server when windows/pw is really started, power up the supporting servers any order.

    For our remote offices we sometimes see a need to restart the caching server\service if the main intergration server is shut down.

    Answer Verified By: Neil Norberg 