I'm using ProStructures Connect Edition Update 4.
Can I use 2 different rebar codes within one design model?
I need to use MMFX code for curbs and top slab in my concrete box culvert, then RSIC code for the remainder.
Is there a recommended suggested workflow?
Or do I reference in the rebar details of one code so as to ensure I'm lining up rebar correctly?
Hi Nicole,
Thanks for posting your query in Bentley Community Forum.
I am not sure about this. Let me test investigate on that aspect and will get back to you.But recommended workflow is to use one Code per DGN. Need to investigate if one can use mixed rebar code.
Regards,Sandip KarProduct Engineer - Bentley Systems
OK thks Sandip.
Nicole Joyal
Bridges & Highway Structures
Manitoba Infrastructure
Canada
Hello Nicole
Have you been considered work the two files in a workset with a dgn file as attachment?
Regards, Randolf