I attach ALL references with relative paths to a project
This does not always occur. see below
I makes me have to review another version of the Franchise that is subtly different - takes 1-2 days just to verify if things are linked correctly.
This issue is being worked through a Service Request, but has anybody else run into issues after copying projects?
Hi Larry
Is it possible to re-path a raster reference file using the raster manager? Ordinary vector references are simple, but raster images seem to have another set of rules....
Stuart_H
I don't see a way to re-path a raster attachment the way you can for vector reference files.
Not even through Properties of the raster file in Raster Manager.
The only way I found to relocate a raster attachment is to detach/re-attach.
Platform Support may be able to give you more information.
Larry