Hi.
I brought in beam sizes to my RAM model from Revit using ISM. The sizes are showing up fine. The problem I have is that number of studs have changed to zero. Is there a way to automatically change the studs to the correct number? The only way I can think of is to manually change them using "View/Update" command. There are about 1500 beams total and this will be very time consuming. See screenshot below. the beam with (12) studs was changed manually.
Thank you,
Seth, I already had that option selected. What I ended up doing was "assign" beam size and re run design. That reduced the amount of time significantly. Thanks for your help as always.
If the assigned number of studs was too few for minimum composite action this might happen. If so, then changing the stud criteria, to design based on composite properties even when the percentage is too low before running design would preserve the assigned stud count I believe.