Does 25% increment for group of pile is applicable in lateral load cases?
As per code 25% increment is applicable for one pile for lateral load. For individual pile in a group of piles, the check is performed for 125% of pile capacity. However for group of piles, the 25% increment can’t be applied. For more information refer “Technical discussion” of Pile-cap from help Content.