Hi,
I'm using ORD 10.07.00.56 with Projectwise 10.00.03.167.
When I apply a point control from a referenced corridor, it works fine until I reopen my dgn file. The referenced corridor is still attached, but the points I have just assigned are no longer there...
Projects that I was not using PW didn't have this problem. Would this problem be linked with PW?
Has anyone experienced this issue?
Thanks,
Pat
I would check to see if the dgn is being checked in properly and saving off the changes that you make. You could also test by opening the local copy of the dgn in the dms location to see if it is saved there.
https://communities.bentley.com/products/road___site_design/w/road_and_site_design__wiki/42035/projectwise-integration