OpenRoads 2020 R3 10.09.00.91
Hello,
I am trying to run earthwork on my proposed corridor. I have the existing pavement modeled in a separate DGN. Is there a way to tell the earthwork analysis to exclude the existing pavement from the excavation area? The pavement removal is a separate pay item, so I do not want the green end area for the excavation inside of the existing pavement area. Thanks!
Ben
See this video https://communities.bentley.com/products/road___site_design/w/road_and_site_design__wiki/55061/video-create-cut-fill-volumes---unsuitable-materials
and note that the feature definition volume option determines how the mesh volumes are generated and reported as described
here https://communities.bentley.com/products/road___site_design/w/road_and_site_design__wiki/42267/what-do-each-of-the-volume-options-mean-for-the-mesh-property-feature-definition
I'm still having issues with this... I'm trying to get accurate earthwork shown in cross sections using end area method using "quantity report by named boundary". I have the volume option set to "Unsuitable" for the existing pavement i have referenced into my Corridor Model, but it still looks like the Cut Area is including the existing pavement.