OpenRoads 2020 R3 10.09.00.91
Hello,
I am trying to run earthwork on my proposed corridor. I have the existing pavement modeled in a separate DGN. Is there a way to tell the earthwork analysis to exclude the existing pavement from the excavation area? The pavement removal is a separate pay item, so I do not want the green end area for the excavation inside of the existing pavement area. Thanks!
Ben
I'm still having issues with this... I'm trying to get accurate earthwork shown in cross sections using end area method using "quantity report by named boundary". I have the volume option set to "Unsuitable" for the existing pavement i have referenced into my Corridor Model, but it still looks like the Cut Area is including the existing pavement.
See this video https://communities.bentley.com/products/road___site_design/w/road_and_site_design__wiki/55061/video-create-cut-fill-volumes---unsuitable-materials
and note that the feature definition volume option determines how the mesh volumes are generated and reported as described
here https://communities.bentley.com/products/road___site_design/w/road_and_site_design__wiki/42267/what-do-each-of-the-volume-options-mean-for-the-mesh-property-feature-definition