Inroads/Microstation, Rail Vertical Alignment coordination with Road Grade Crossing Vertical Alignment

Hello All,

Let me start with a description of the work..

Approx. 130 Miles of Proposed Track to run along existing Track. 

Approx. 260 Grade Crossings.

Is there anyway to automatically import Track Vertical Elevation for each Cut of Roadway Grade Crossing Profile to confirm the tie in point to be accurate and consistent with track alignment when crossing the each of 260 grade crossing roads? 

Initially, I had to import 1 station at a time from the intersecting Station that  I gathered from using the Export Geometry Intersecting Tool. 

FYI- We started learning inroads when this project started but are realizing it is a much powerful tool than Geopak. Anyways, any help to facilitate this would be greatly appreciated. As you can imagine seeing the amount of work and coordinating with track/road, this can be time consuming. 