Wire Tag Link auto change

Dear Sir!

When I change Location of Project, all Wire link tag are automatically changed to new name which is default in promis.e. 

I want when I change locaition of project , Wire link tag is not changed, 

Please help me!

I use : promise_series_5_v08.11.10.66_x64, 

  • You don't say what command you used to "change the location".  However, based on some of your previous questions about moving page, I might guess you were using the Page Move command.  When you move the page, the left side of the dialog has several choices for you to make about the names of the new pages, including assigning it a new Location name.  The right side of the Move Page command has a number of check boxes to define how you want the software to rename the items on the pages, such as Device ID's. Wire numbers, and Wire Link ID's.  If you had the check box for "Maintain Wire Link ID's" checked and the pull down set to "Complete", then no change should have occurred to your Wire Links.  (The "Tag only" choice would keep the same Tag name but taken on any new values you had typed in for Installation or Location names.)   But if you did not have the checkbox set to Maintain Wire Link ID's, then the software would renumber the Wire Link ID's to the project default because you told it you wanted to renumber those items, not maintain their current ID's.  You should make sure that you are carefully checking all the settings in the tool dialog before you click to execute the command.  

    If you were using some other command, please let me know which one, but most tools that involving changing names also have similar options to let you chose to rename the items on the pages as well.

  • Hi, i would like to re-open that question. 

    When updating the installation/location of the project, the wire links are updated automatically --> but only if the wire link has defined location. In case, where the location was empy, the wire link ID has not been correctly updated. Why?

    Second - is there a tool, to batch update of wire links? 

  • Hi Tomasz,

    Can you provide more details on your work flow for the issue you are facing with the Wire Link? Also can you confirm the tool you are using to update the Installation/Location of a page or equipment? 

    You can use the Data Manager tool to update multiple wire link details. Kindly refer the below image for steps to use Data Manager. Let us know if you have any questions or concerns with using Data Manager.