There are users who might need to place the Reports generated using Run Reports on Project Pages. This article can be referred to by users on how to place reports on New / Existing Project Pages.
A. Existing Page
B. New Page
1. Open/Create a Project Page where the Report needs to be placed.
2. Go to Output >> Run Report.
3. Select Report >> Apply filter (If needed) >> Text On Drawing.
4. select Existing Page >> Ok >> Click on the DGN where the report needs to be placed.
1. Open any Page in the project.
2. Go to Output >> Run Report.
3. Select Report >> Apply filter (If needed) >> Text On Drawing.
4. Select New Page >> Fill in all the details on Page Margins or Row Settings >> Click OK.
5. Then in the New Page dialog select Page Settings along with Page Name where the report needs to start and click Ok.
Original Author: | Satish Saptasagar |