Browse By Tags

  • short-term and long-term composite cross-section

    Hi all. In composite steel girder bridges with concrete decks (continuous span bridges), does RM bridge automatically Calculator effective width of deck to calculate short-term and long-term composite cross-sections? best regards.
  • Steel composite bridge

    Hi all. I hava some question about steel composite brige as follows: 1. To calculator stress point of section, Rm Bridge automatic use short-term section for live load and load case type Non-permanent and use long-term section for load case type Permanent…
  • Post-Tensioning of AASHTO I Girder Type LEAP Bridge Concrete

    June 24, 2017 Dear Engineers, Greetings for all structural engineers in the world. I'm a bridge engineer from the Philippines and currently connected in a consulting firm. I'm using Leap Bridge Concrete for less than a month and find out that it…