• Horizontal shear method and result

    Donghee Ko
    Donghee Ko
    I don’t know when I use “include beam and slab contribution in Vu” and “Exclude Beam and Slab contribution form Vu” why are V vh-rg values zero?
    • over 3 years ago
    • LARS | LEAP | OpenBridge | OpenTunnel | RM
    • LARS | LEAP | OpenBridge | OpenTunnel | RM Forum
  • LEAP Bridge Concrete DW loads

    Tucker Raney
    Tucker Raney
    How does LEAP Bridge Concrete calculate the reactions for DL-Comp. (DW)? I added up all the DW reactions and compared to a hand calc of utlities and overlay loads. The total DW is nearly 4 times greater than my hand calcs. I have 4 beam lines with 0.05…
    • over 6 years ago
    • LARS | LEAP | OpenBridge | OpenTunnel | RM
    • LARS | LEAP | OpenBridge | OpenTunnel | RM Forum
  • Conspan 10th points

    Nick Caron
    Nick Caron
    From what I understand Conspan calculates 10th point increments from the total precast length and not the bearing to bearing span length. Is there a way to get camber and deflection readouts at the bearing to bearing 10th points? All the DOTs in New England…
    • over 7 years ago
    • LARS | LEAP | OpenBridge | OpenTunnel | RM
    • LARS | LEAP | OpenBridge | OpenTunnel | RM Forum
  • Detensioning Failure

    Stephen Fussnecker
    Stephen Fussnecker
    I have a single span bridge using I-girders that I need close to the max amount of strands in. These are all straight strands, and I've had to debond to 4 different lengths from the end. The longest debond is 25' of my ~90' girder. When I look at the…
    • Answered
    • over 8 years ago
    • LARS | LEAP | OpenBridge | OpenTunnel | RM
    • LARS | LEAP | OpenBridge | OpenTunnel | RM Forum
  • View related content from anywhere