Is presented below the Rating Factor calculation done in OBD / RM Bridge for a two spans composite steel bridge with a central pier.
Bridge Modelling done in OBM and calculation performed in RM on a complete model in OBD.
Table of Contents:
A…
RM > Modeler definition of slender parts in cross-section.
Cross-Sections – Slender Parts:
Required for the local buckling.
Reference Set – Steel Slender part type
Start point = free point
Line point = restraint point
Subtype of slender…
In OBD CE 2021 Release 2 and RM Bridge v11.13, was implemented the Ultimate Check Capacity using different types of force component selections namely: Total: Normal, Total: Split and, Total: Join . The non-composite cross-section defaults to the Total…
In this video is presenting the Last Construction Stage after the concrete slab is hardened and composite elements activated.
It is introduced the load cases for deck wearing surface and utilities, the earth pressure behind abutments, the transferring…
In RM Bridge Enterprise > Modeler > Cross sections, the User can define the finite shell elements in the deck slab.
The User can edit shell elements for assigning variables to slab thickness, if desired and review the information introduced.
In…
In RM Bridge Enterprise > Analyzer, were defined the several Construction Stages considered in the bridge built and until the composite is activate (before concrete slab is hardened). Presented below the different construction stages calculated.
STG01…
In RM Bridge Enterprise > Modeler, was defined the completely geometry for an Integral Steel Composite Bridge. In this video series, it is presented the structural analysis and design for this type of bridges.
The deck cross-section is defined with…
Inside File\Examples\Training Examples user can select in the list the Steel Design Training Example with the options for a. Eurocode and b. AASTHO , as shown in the image below. The definition of slender cross section parts are shown in the Properties…
I am currently design 4 bridges in LEAP Steel v19 but am encountering an issue with the tool to automatically generate loads for the wearing surface of the structure.
The bridges are all of a similar type, but some are wider than others and one is on…