• Tags
  • Subscribe by email
  • More
  • Cancel
  • New product line RM Bridge Advanced+ V8i v08.11.11.01

    Andreas Rock
    Andreas Rock
    New product line RM Bridge Advanced+ V8i  v08.11.11.01 Index 1. About the RM Bridge V8i v08.11 products 1.1 RM Bridge V8i 1.2 RM Bridge Advanced V8i 1.3 RM Bridge Cast V8i 1. About the RM Bridge V8i v08.11 products


    The new RM Bridge V8i v08.11 product line is the next major release of the renowned and widely used software suite RM Bridge V8i.

    The software performs analysis and design of arbitrary bridge structures…

    • Wed, Nov 20 2013
  • What's New & Changed in RM Bridge V8i v08.10.18.01

    Andreas Rock
    Andreas Rock

    What´s New & Changed in RM Bridge V8i v08.10.18.01 Index 1. About the product 2. Improvements in Detail 2.1 GUI – Enhancements 2.2 RM2Rebar 2.3 Earthquake Analysis 2.4 Tendon geometry 2.5 Steel design 2.6 Wizard 2.7 Localisation 2.8 Loading 2.9 FEM 2.10 Documentation and Examples 1. About the product

    RM Bridge V8i (SELECTseries 3)  is the 4th major release (July 2012, maintenance release…

    • Thu, Sep 5 2013
  • New Update LARS Bridge v5.00.06.09 available on SELECT Server

    Rita Oglesby
    Rita Oglesby

    General

    1. Fix for LRFR live load various distribution factor values were defined in various spans of continuous structures.

           2.   Fix for ASD/LFD/LRFR live load symmetry.  A larger live load value was sometimes computed.  Changes have been made to the lane live load computation which will result in a slight increase or decrease of the previously computed value.

           3.   Fix in Echo.lis when reporting nonstandard truck axle…

    • Mon, Jun 10 2013
  • Coming Soon: LEAP Bridge Steel - NASCC preview

    Sri
    Sri

    If you are visiting NASCC, The Steel Conference, in St. Louis, MO, April 17-19, 2013, please stop by the Bentley booth (#919) for an exciting preview of our sophisticated new offering for Steel Bridge Design.

    • Tue, Apr 16 2013
  • Just Released: New App for Bridge Inspection

    Sri
    Sri

    Bridge Inspectors have a new level of mobility with InspectTech Collector Mobile on the iPad. This app enables quick and effective collection of transportation infrastructure asset information and completion of inspections in the field. A streamlined interface delivers valid fields and drop-downs as the inspector works through a logical and thorough collection of data. Support for rich data such as photos, video, and…

    • Wed, Mar 6 2013
  • RM Bridge´s New Features and Improvements December 2012

    Andreas Rock
    Andreas Rock
    New Features and Improvements

    In past months several enhancements have been implemented in RM Bridge V8i version. Due to the variety of new functions we decided to create a short summary of the comprehensive functionality in form of document.
    We are encouraging you to accept the challenge of using them and giving us feedback of your experience as well as new ideas, which will serve you during your bridge analysis and…

    • Fri, Dec 21 2012
  • What´s New & Changed in RM Bridge V8i v08.10.12.01

    Andreas Rock
    Andreas Rock
    What´s New & Changed in RM Bridge V8i v08.10.12.01   Index 1. About the product 2. Improvements in Detail 2.1 GUI – Enhancements 2.2 RM2Rebar 2.3 Earthquake Analysis 2.4 Tendon geometry 2.5 Steel design 2.6 Wizard 2.7 Localisation 2.8 Loading 1. About the product

    See also release notes RM Bridge V8i (SELECTseries 3)  v08.10.12.01.

    RM Bridge V8i (SELECTseries 3)  is the 4th major release…

    • Fri, Dec 21 2012
  • Bridge Information Modeling: Design and Engineering Collaboration Webinar

    Sri
    Sri

    In case you've missed it, here is a link to an excellent presentation by Finley Engineering Group, Inc. (FINLEY).

    http://www.roadsbridges.com/bridge-information-modeling-design-and-engineering-collaboration

    Webinar Overview:

    Bentley provides the world’s most comprehensive solution for Bridge Information Modeling (BrIM). At the core of this solution are MicroStation, RM Bridge, and Bentley Rebar. This overview of…

    • Tue, Dec 18 2012
  • New Release - LEAP Bridge V8i SELECTseries 5 (v12.01.00.57) - now available

    Sri
    Sri

    LEAP Bridge v12.01.00.57

    Enhancements:

    • Introduced a new analysis option “Integral Abutment Bridge” in the Project tab. This option allows users to analyze and design integral abutments.
    • Support for Pile Bent and Wall Pier Type abutments has been added. ABC Wizard custom definition, 2D and 3D drawings and transfer of information to RC-PIER and Geomath are now supported.
    • The variable cap definition in…
    • Mon, Dec 10 2012
  • New maintenance release RM Bridge V8i (SELECTseries 3) v08.10.07.02 is available

    Andreas Rock
    Andreas Rock


    RM Bridge V8i (SELECTseries 3) v08.10.07.02 is a maintenance release for v08.10.07.01

    We recommend using it as your new production release. It fixes reported common problems of the main release:

    • ULTCHK: Reinforcement defined at composite was not considered – fixed
    • ULTSUP: Tendon results were not treated correctly – fixed
    • CANTILEVER : Module did not work properly - fixed
    • Element-CS: Editing an element…
    • Mon, Aug 13 2012
  • What's New and Changed in RM Bridge V8i(SELECTseries 3) v08.10.07.01

    Andreas Rock
    Andreas Rock

    Index 1. About the product 2. Improvements in Detail 2.1 RM2Rebar 2.2 Earthquake Analysis 2.3 Tendon geometry 2.4 Steel design 2.5 Localisation 1. About the product

    See also release notes RM Bridge V8i (SELECTseries 3)  v08.10.07.01.

    RM Bridge V8i (SELECTseries 3)  is the 4th major release (July 2012) of the renowned and widely used software suite RM Bridge V8i, succeeding RM2006 in 2009. The software performs…

    • Sat, Jul 21 2012
  • New Update LARS Bridge v5.00.06.08 available on SELECT Server

    Rita Oglesby
    Rita Oglesby

    LARS Bridge General Enhancements and Fixes

    • Critical bug fix for floor beam live loading.  The issue occurred only when the default edge distance was 18” and the Description è General Bridge Information è Edge Dist. was set to 24”
    • Compute impact factors at exact checkpoints.  This value was not previously computed.
    • Critical fix Floor beam
    • Critical bug fix for LRFD lane load which was reduced…
    • Mon, Jul 16 2012
  • CE News Webcast Recording: Replacing the Katrina-Damaged I-10 Twin-Span Bridges

    Sri
    Sri

     Watch Now!

    Discover how the Louisiana Department of Transportation and Development integrated design efforts across multiple teams and locations to complete their bridge project under budget and ahead of schedule!

    • Mon, May 21 2012
  • Bentley Acquires InspectTech, Leading Provider of Software-as-a-Service for Bridge Safety

    Sri
    Sri

    An exciting new addition to the Bridge Product line at Bentley rounding off the bridge asset life cycle management, all the way from design to maintenance and inspection.

    Bentley Systems, Incorporated, the leading company dedicated to providing comprehensive software solutions for sustaining infrastructure, today announced at this gathering of infrastructure professionals from around the world that it has acquired InspectTech…

    • Mon, May 21 2012
  • New Update LARS Bridge v5.00.06.06 available on SELECT Server

    Rita Oglesby
    Rita Oglesby

    LARS Bridge General Enhancements and Fixes

    • LLDF Cross-Section Description dialog now applies to each member instead of each bridge.   This will allow a User to define different beam spacing and roadway width for each member.  There is no visible change in LARS Bridge for this enhancement.   Any existing files with data in the LLDF Cross Section Description dialog  should be saved in LARS Bridge v5.00.06.06 so that LARS…
    • Tue, Apr 17 2012
  • What's New and Changed in RM Bridge V8i(SELECTseries 2) v08.10.03.01

    Andreas Rock
    Andreas Rock
    Index

    1. About the product 2. General GUI Enhancements 3. Templates, Macros, Preprocessors 4. Wizards 5. Steel Checks 6. Pre-tensioned Girders 7. Miscellaneous Functional enhancements 8. Localization

    1. About the product

    RM Bridge V8i (SELECTseries 2)  is the 3rd major release (March 2012) of the renowned and widely used software suite RM Bridge V8i, succeeding RM2006 in 2009. The software performs analysis…

    • Thu, Mar 29 2012
  • LARS product line update

    Rita Oglesby
    Rita Oglesby

    Bentley’s Bridgekey product line is now the LARS product line.  Also, all of the LARS products are now utilizing the “SELECT series 2” licensing.  The individual products names have also been changed.  The name changes are:

    • BridgeKey BridgeModeler/LARS à LARS Bridge
    • BridgeKey Complex Truss à LARS Complex Truss
    • BridgeKey DataChecker à LARS Checker
    • BridgeKey DataConnector à…
    • Wed, Aug 24 2011
  • LEAP Bridge V8i (SELECTseries 2) maintenance release v10.00.02.19 now available on SELECT

    Sri
    Sri

    LEAP Bridge v8i (SELECTseries 2) v10.00.02 is a maintenance release and incorporates the following fixes to itself and its component programs:

    LEAP Bridge v10.00.02

    Fixes:

    • Fixed an error in LEAP Bridge, where if the user selects EXIT option in CONBOX, LEAP Bridge was closing.
    • Automatically minimize LEAP Bridge, when a component application is minimized.
    • Automatic bearing location algorithm now considers bottom…
    • Tue, Aug 23 2011
  • LEAP Bridge Infographic

    Sri
    Sri

    • Fri, Jul 15 2011
  • New Update LARS Bridge v5.00.05.01 *** now available

    Rita Oglesby
    Rita Oglesby
    • LARS Bridge v5.00.05.01 issues fixed
    • Live load distribution factors were changing for all member when only one was changed
    • The Bridge ID didn’t save more than 6 characters
    • Modified live load distribution factors weren’t saved
    • Corrected any issue Single floor beam distribution factor when using MODOT’s multiple/single LLDF enhancemenr
    • No production releases for version v5.00.02.00,  v5.00.03…
    • Tue, Jul 12 2011
  • Bridge Engineer? Create your own 3D Bridge Models ...

    Sri
    Sri

    Always wanted to create your own 3D Bridge Models for use in presentations and reports? Using LEAP Bridge this is real easy and ultra cool. Most importantly it is the same structural model that is used to analyze and design your bridge. A simple byproduct of your everyday work!

    Simply use the ABC Wizard, where you could model realistic looking concrete bridge models, complete with Abutments, intermediate piers, bridge…

    • Wed, Jun 15 2011
  • New Release: LEAP Bridge V8i (SELECT series 2) v10.00.01.20 - Coming Soon ...

    Sri
    Sri

    LEAP Bridge v8i (SELECTseries 2) v10.00.01 is a new release which incorporates numerous enhancements. 

    LEAP Bridge v10.00.01

    Enhancements

    • ABC Wizard now allows users to model T beam bridges, reinforced or post-tensioned.
    • ProjectWise integration is now available directly from within LEAP Bridge. Open, Save and Update files directly from ProjectWise repositories. .
    • Specify or edit bearing and beam…

    • Wed, May 4 2011
  • The Sheikh Zayed Bridge in Abu Dhabi

    Sri
    Sri
    SHEIKH ZAYED BRIDGE
    Location: Abu Dhabi, U.A.E.
    Description: A twin deck bridge comprising prestressed concrete box girders supported by bearings on concrete piers and by hangers on a pair of 3D steel arches. The steel arches are connected to the concrete piers to transfer their loads to the foundation.
    Total length: 842 m (2762 ft.)
    Main span: 140 m (459 ft.)
    Owner: Works Department, Emirate of Abu Dhabi
    Client: Archirodon…
    • Wed, Nov 24 2010
<